xvii. Project authorities shall inform the Regional Office as well as the Ministry, the date of financial closure and final approval of the project by the concerned authorities and the date of commencing the land development work.
8.0 The Ministry may revoke or suspend the clearance, if implementation of any of the above conditions is not satisfactory.
9.0 The Ministry reserves the right to stipulate additional conditions if found necessary. The Company in a time bound manner shall implement these conditions.
10.0 Any appeal against this environmental clearance shall lie with the National Environment Appellate Authority, if preferred within a period of 30 days as prescribed under Section 11 of the National Environment Appellate Act, 1997.
11.0 The above conditions shall be enforced, inter-alia under the provisions of the Water (Prevention & Control of Pollution) Act, 1974, the Air (Prevention & Control of Pollution) Act, 1981, the Environment (Protection) Act, 1986, Hazardous Wastes (Management and Handling) Rules, 2003 and the Public (Insurance) Liability Act, 1991 along with their amendments and rules.
(Dr. P. B. Rastogi)
Scientist ‘F’
Copy to :
1. The Secretary, Department of environment and forests, Govt. of Gujarat, Gandhi Nagar,Gujarat.
2. The Chief Conservator of Forests (Central), Ministry of Environment & Forests, Regional Office (West), Link Road No. 3, E - 5, Arera Colony,Bhopal - 462 016, M. P.
3. The Chairman, Central Pollution Control Board Parivesh Bhavan, CBD-cum-Office Complex, East Arjun Nagar, New Delhi – 110 032.
4. The Chairman Gujarat Pollution Control Board, Paryavaran Bhawan, Sector 10-A, Gandhi Nagar – 382 010, Gujarat.
5. Scientist ‘G’ (IA), Ministry of Environment and Forests, Paryavaran Bhavan, CGO Complex,New Delhi.
6. Monitoring Cell, Ministry of Environment and Forests, Paryavaran Bhawan, CGO Complex,New Delhi.
7. Guard File.
8. Monitoring File.
9. Record File.
(Dr. P. B. Rastogi)
Scientist ‘F’